The Preparatory Work to the Test Run of Ball Mill

14.May.2018 info@hxjq.com

The Preparatory Work to the Test Run of Ball Mill

As we all know, it must have a test before the newly installed ball mill takes the formal operations of crushing work. The hidden problems can be found out in the process of test operation, which is convenient to correct and improve for the manufacturer. In addition, it is an important basis for users to buy the troubleprool equipment.

What are the requirements when test ball mill? What needs to be done for the preparatory work? They are the necessary works to the manufacturers when the test run is done before delivery. The followings are the detailed explains of our professional technician.

ball mill

First of all, we should check the cleaning work of ball mill. The residual materials and sundries must not be stayed in ball mill.

There are many aspects for the cleaning work. For example, check whether there are sundries in feed and discharge port and vacuum tube of ball mill; clean bearing and the outer cylinder. What’s more, pay attention to remove the debris near the ball mill, so as not to affect the operator's view.

Secondly, before the test run, the oil tube leading to the equipment needs to be disassembled, and close off oil inlet by using blind plate.

The detailed method :

Connect the inlet tube to the outlet pipe by the temporary pipe, and then rinse it with a circulating pump. The rinsing standard is that there is no sundries in oil filter. Finally, rinse the oil tube by using the circulating pump, and then connect it to ball mill.